DoMa pipeline construction project

Important pipeline in the GET H2 network

The DoMa pipeline runs from Dorsten to Marl in the district of Recklinghausen where the chemical park has a high demand for hydrogen which can be supplied via the GET H2 network. The partners in this project are Open Grid Europe GmbH (50 per cent) and Nowega (50 per cent).

Facts and figures

9 KM

Pipeline length

buried

Type of installation

70 bar

Design pressure

DN 300

Pipe diameter

-

Construction

2027

Completion

Planning status

Following the regional planning assessment by Regionalverbund Ruhr in winter 2022, OGE is now preparing the documents for the planning approval process.

In June 2023, the project sponsor OGE organised a number of Dialogue Markets featuring themed stands and project maps to inform the public about the next steps in this project, and local citizens had the opportunity to talk to OGE and the project partners and gain further insights into the project.